Narre Warren Bridge Drainage Upgrade

Project Information

Location: Narre Warren
Client: City of Casey
Service Category: Drainage
Duration: 4 weeks

Project Overview

Drainage and erosion works for City of Casey alongside a creek at Narre Warren, carried out to Melbourne Water specifications. The scope covered erosion control and rock beaching to protect the creek bank, managing water flows through the site while works were under way, and civil reinstatement including kerb and channel and asphalt repairs.

Scope of Works

Erosion control and rock beaching to Melbourne Water specification
Water flow management through the works area
Kerb and channel
Asphalt repairs

Challenges

Working in and around a live creek, where managing water flows was central to getting the job done safely and to spec. The crew had to keep the channel functioning while building permanent erosion protection in the same footprint, all inside a tight one month window.

Outcome

Completed on time and on budget, with positive feedback from both City of Casey and Melbourne Water on the standard of the finished works.