Project Information
Location: Mount Eliza
Client: Mornington Peninsula Shire
Service Category: Drainage
Duration: Ongoing
Project Overview
APS Civil is delivering the sewer and electrical early works package at Emil Madsen Reserve in Mount Eliza, ahead of a new pavilion being built at the reserve.
Early works packages like this one set up everything that sits below ground before the main building contractor arrives. Getting the services in, connected and to the right levels first means the pavilion build can start without hold-ups later.
Emil Madsen Reserve is a working sporting and community reserve, so the site has stayed open and in use throughout. The clubrooms, playground, skate park and open space all remain accessible while the works are carried out around them.
Scope of Works
- Sewer connection to the rising sewer main to service the new pavilion
- Decommissioning and removal of the existing septic tanks
- Trenching and pipe installation, with shoring used throughout for safe working depth
- Electrical upgrade to allow connection of the new pavilion and to allow for future building works at the reserve
- Site establishment, fencing and traffic management to keep the reserve open and safe
- Reinstatement of disturbed areas
Challenges
Weather has been the biggest factor. The works have run through a consistently wet stretch, with rain making trenching, shoring and reinstatement harder and slowing progress in ground that stayed saturated for long periods.
The other constraint is working within a live site. The reserve is used by clubs and the public throughout the week, so the work zone has had to be kept tight and clearly separated, with access maintained to the clubrooms, car park and surrounding facilities at all times.
Outcome
Works are ongoing. Once complete, the sewer and electrical infrastructure will be in place to support the new pavilion and to allow for further development at the reserve down the track, giving the clubs and the wider community better facilities to use.